Maintenance of the entire infrastructure
Completed
Scheduled for 28.12.2023 at 07:00:00 – 17:47:42
Affects
Serverhousing
Under maintenance from 7:00 AM to 5:47 PM
Housing-Services Area 1
Under maintenance from 7:00 AM to 5:47 PM
Housing-Services Area 2
Under maintenance from 7:00 AM to 5:47 PM
Housing-Services Area 3
Under maintenance from 7:00 AM to 5:47 PM
Housing-Services Area 4
Under maintenance from 7:00 AM to 5:47 PM
Managed Workload services
Under maintenance from 7:00 AM to 5:47 PM
Updates
Completed
28.12.2023 at 17:47:42
Completed
28.12.2023 at 17:47:42
There have been no operational disruptions in the last few hours - the maintenance window has therefore ended.
Update
28.12.2023 at 13:33:41
In progress
28.12.2023 at 13:33:41
Unfortunately, there was a power interruption during maintenance of the power supply, which resulted in a defective switch.
We exchanged the corresponding component for a switch from the redundancy stock and were thus able to restore functionality.
All systems are currently starting up again.
In progress
28.12.2023 at 07:00:01
In progress
28.12.2023 at 07:00:01
Maintenance is now in progress
Planned
28.12.2023 at 07:00:00
Planned
28.12.2023 at 07:00:00
Planned maintenance work will take place in the data center on December 28, 2023 from 8 a.m. to 2 p.m. - there will be restrictions in the availability of individual services and servers - please take this into account when planning work on the corresponding day.